Argentina, Uruguay At Loggerheads Over Pulp Mills on Shared River

BUENOS AIRES, Argentina, May 9, 2006 (ENS) - A heated dispute between Argentina and Uruguay over two pulp mill projects, currently under construction on the eastern shore of the Uruguay River, a natural resource shared by both countries, has both governments steaming.

Argentina filed a case against Uruguay over the mills in the International Court of Justice in the Hague on May 4. The next day, Argentine President Nestor Kirchner led provincial government officials and others in a protest against the mills in the town of Gualeguaychú.

demonstration

Argentine President Nestor Kirchner addresses the demonstration May 4 against two pulp mills in Uruguay. (Photo courtesy Office of the President)
The filing is the first time that a Latin American country has taken a neighboring state to international court over an environmental dispute. It is also the first time that a World Bank project will be the focus of a case at the International Court of Justice.

For its part, Uruguay has filed a claim with the Secretary General of the Organization of American States and invoked the Olivos Protocol within the framework of the MERCOSUR trade agreement to seek a political solution. The mills have been approved by the Uruguyuan government, and construction has started.

The mills are being built by Finnish company Metsa Botnia and Spanish company Ence in the vicinity of Fray Bentos, Uruguay near the border between the two countries. Their total combined cost is estimated at US$1.8 billion.

Plans call for the mills to use elemental chlorine free technology to manufacture bleached eucalyptus pulp for export.

Ence’s project is a plant with an output of 500,000 tons of pulp per year, while that of Metsa Botnia would have an output of 1,000,000 tons per year. These factories are expected to produce 1.5 million tons of cellulose, one of the largest outputs in the world and "a very significant environmental challenge," the Argentine government said.

Argentina complains that Uruguay authorized the construction of the pulp mills and of a port for the exclusive use of one of them without following the mechanism of consultation and prior information agreed by both countries in the treaty of 1975 on the Statute of the Uruguay River.

"This mechanism is in conformity with international environmental law and the principle that no country should allow activities within its jurisdiction or under its authority which can have a negative environmental impact on a neighboring country, a principle that both countries have fostered in a number of international treaties and agreements," the Argentine government said Monday in an official memo sent to ENS.

The government of Uruguay is eager to see the pulp mills go ahead. Tabaré Vasquez, Uruguay’s president met May 3 with World Bank President Paul Wolfovitz in an effort to get explicit Bank approval for the projects. The mills, which have not yet received World Bank funding, are under consideration by the International Finance Corporation and the Multilateral Investment Guarantee Agency to receive over US$400 million.

Local people are worried about environmental pollution, deforestation and increased truck traffic.

In April, Argentinian protesters blocked a highway into Uruguay protesting the mills on environmental grounds. The roadblock was lifted on May 2, but concerns that mills will ruin the sensitive river ecosystem and the area's tourist industry drew about 100,000 people to a rally against the mills in Gualeguaychu on April 30.

mill

Botnia Pulp mill project area in Fray Bentos, on the Uruguay River. (Photo courtesy Greenaccord)
Large public demonstrations against the two pulp mills are not new. On April 30, 2005, some 20,000 people from Argentina and Uruguay met in the middle of the international bridge joining the two countries near Fray Bentos to express their opposition to the mills.

In an open letter to the International Finance Corporation (IFC) on June 3, 2005, dozens of environmental groups from both countries as well as concerned individuals object that the Uruguayan government's environmental analyses were done for each plant separately and did not take into account the accumulated environmental impacts of the two pulp mills together.

In their letter to the IFC the critics say that neither Metsa Botnia nor Ence have carried out any serious studies on the possible negative social impacts of their projects, either in the matter of foreseeable loss of jobs related to the liquid effluents, and to gaseous emissions with a strong and disagreeable smell, of the pulp mills, or of the possible impacts on the health of the local population.

"At no time has it been considered that some 1,300 people in Fray Bentos, out of an economically active population of 8,500, obtain employment from local tourist activities, linked to the Las Cañas resort, which would be threatened by the presence of two enormous pulp mills a few kilometers upriver from the tourist zone," the letter states.

To them are added a "non-quantifiable" number of fisher-people and honey producers who might also lose their means of livelihood if these plants are installed, the groups wrote to the IFC.

The possible negative social impacts on the Argentine side have not been considered either, where they also depend on tourist activities as a generator of employment, the critics said.

The groups point out that timber requirements to supply both mills are much higher than local supply, even if it were also to come from both countries.

It is also important to point out, they said, "the impacts that one or both plants would have on the use of the country’s highway facilities due to the traffic of hundreds of trucks with 40 ton loads or more."

Metsa Botnia will require 3.5 million cubic metres of eucalyptus timber, while Ence requires 1.7 million cubic metres. With these requirements, the groups estimate that there will have to be an annual cutting of 140,000 hectares (540 square miles) for Metsa Botnia alone and 210,000 hectares (810 square miles) per year for both plants.

The installation of one or of both plants would imply tripling the present area under plantation, the groups told the International Finance Corporation, hoping head off the loan.

The Center for Human Rights and Environment (CEDHA), an environmental lobby group with an office in Argentina, says Botnia, the Finnish pulp mill was to blame for the recent collapse of negotiations between Argentina and Uruguay to resolve the dispute.

sign

Argentine Vice President Daniel Scioli (left) and President Nestor Kirchner hold a sign at the rally May 2. It reads, "Yes to life, no to the pulp mills." (Photo courtesy Office of the President)
Fearing a drop in stock values in New York, the company decided to ignore the presidents’ request to halt construction, allowing the two nations to sort out their differences. This decision left the negotiators without information regarding eventual impacts to the environment, to the impacted region’s tourist industry and to the health and livelihoods of local communities threatened by the pulp mills’ expected pollution.

CEDHA argues that Botnia and ENCE are using second-rate technology that is being phased out in Europe. The companies have to turn to countries with less stringent environmental laws to build their mills, CEDHA says.

While the pulp bleaching process would be chlorine-free, CEDHA says the waste produced by the pulping and bleaching stages of the process would contaminate the environment.

CEDHA claims that dioxins, carbon monoxide and sulfur dioxide would be discharged into the air and into the River Uruguay, which is used for drinking water by nearby towns. Large volumes of fresh water would be extracted from the river for the mills, and plantation expansion would see native vegetation cleared.

The government of Argentina expressed disappointment that a High Level Technical Group entrusted with direct negotiations failed to make a breakthrough despite meeting 12 times between August 3, 1995 and January 30, 1996.

The Argentine delegation to those meetings concluded that due to the polluting nature of the process to be used by the two plants, their magnitude, their geographical location, their proximity to populated and agricultural and cattle grazing areas, the fragility of the aquatic ecosystem, the environment could not be preserved at the highest international levels as both parties had agreed during the Group's first meeting.

 

Entergy Releases 2008 Sustainability Report Plant a Tree for Arbor Day with Mohawk Friends of Animals Win: African Antelope Shielded From Safari Club and Trophy Tourists Green Program Launched to Keep City Parks Poo Free U-Haul Customers Give $1 Million to Charity Core Services Reduces Its Impact on the Environment and Its Use of Natural Resources Women Are the Energy Decision Makers and Want the U.S. to Move Toward Clean Energy, a New National Survey Shows Mohawk Fine Papers Supports Two New Alternative Energy Projects Atrion Leverages Content Expertise to Launch New Generation of RegDBOnline Database for Global Environment, Health, Safety and Transport Information SPIN-Gardening™ Discussion and Action Guide Now Available Medical Experts Prescribe Legislation to Help Prevent Cancer Think London's 'Route to 2012' Olympic Games Roadshow With UKTI Underway With Cleantech Panel Discussion in San Francisco Planet Green's Blue August Month Dives Into Summer With a Celebration of the Oceans Anheuser-Busch Launches Employee Program to Support World Environment Day Hollywood Studios Say No to Plastic Dry-Cleaning Bags and Yes to the Green Garmento Global Advanced Recycling Technology Ltd (GAR-Tech) and Managing Director, Derek W R Reffell, Answer Allegations by PowerMaster Corp. New Green Homes Course and Educational Set Now Available For College Educators Tigo Energy Reaches Key Milestones and Raises $10 Million 'B' Round Financing Atrion First to Deliver Support for EU's new Regulation on Classification, Labeling and Packaging With IA 4.1 GREEN BASH – Multimedia Arts Meet the Green Movement The Global Green Portal Launched NatureAir Receives Prestigious Recognition from World Travel & Tourism Council Master Planning Sustainable Green Communities Energy, Environment and Technology News (EETN) Announces New Blog Monitor Service IC Bus Helps Emeryville, California Go Green With New Hybrid Commercial Buses Natural Selection, Inc. and Empowered Energy Solutions, Inc. Partner for Optimized Renewable Energy Products Architect John Blackburn Launches Eco-Friendly Barn Designs for Equestrian and Agricultural Use Global Advanced Recycling Technology ("Gar-Tech") and Managing Director Derek Reffell Default on Lawsuit Brought by Powermaster Corp. Green Energy Technologies Launches WindCube(R) at Windpower 2009 Thieves Launch New Portable Tetra Pak Wines for Summer NonProfitShoppingMall.com Celebrates Mother's Day and Mother Earth, Naming EarthShare Its Featured Charity Partner for May SustainableBusiness.com/
GreenDreamJobs.com Enters Strategic Partnership with Footprint Media
Virginia Plant Takes Top Environmental Honors in National Cement Awards Fresh Perspective Launches Research Tool for Business Leaders Overwhelmed by Information Pending Bill on Renewable Energy Omits Huge Source Matter Network Has Most Engaged Green Audience, According to comScore Occidental Petroleum's Toxic Legacy in the Peruvian Amazon To Dominate Annual Meeting, Says Amazon Watch New Experience-based Book & DVD Set Offers Unique Opportunity for Understanding Green Homes Siemens Building Technologies: Committed to a Greener, Sustainable Future Save The Planet -- Win a Prize Capital-Intensive Cleantech Innovations May Lose out in Battle to Secure Funding EMS Teams With MATRA for the Rebirth of a Legend: The Limited Edition TidalForce(TM) M-750 x2.0 Electric Bike World's First Green Hotels Directory Launched PR Newswire and World-Wire Join Forces to Showcase Environmentally-Focused News and Events
WW TRANSMIT
 

License ENS News
for websites and newsletters

Send a news story to ENS editors

Upload environmental news videos

Share ENS stories with the world